The bridges and culvert have been installed and look amazing! The Rosebud River and Crossfield Creek bridge installations were complex and critical to complete the trail. Spanning over 160 ft and 120ft respectively the bridges traveled from Ontario and were installed in the week of Nov 25th 2019. Congratulations to the contractor who completed this flawlessly and on time. Also a big congrats to Alberta Trailnet who led this construction initiative! See our pictures tab for updated images including drone footage. Next tasks will be the crushed aggregate layer and signage in the spring of 2020. We will keep you posted on our progress and the grand opening ceremony! Happy Trails!
1 Comment
This open house is to inform the public the process Meadowlark Trail is about to embark on with the construction of the bridges and the culvert:
Fabrication of bridges-> mid-October; Completion of bridges -> mid-November; Active work on site Mid-Oct.; Bridges install mid-Dec. The startup construction meeting will be held with the engineer and the contractor present to answer any questions. The meeting date is Thursday October 10, 7pm-9pm at the Irricana Public Library. |