This open house is to inform the public the process Meadowlark Trail is about to embark on with the construction of the bridges and the culvert:
Fabrication of bridges-> mid-October; Completion of bridges -> mid-November; Active work on site Mid-Oct.; Bridges install mid-Dec. The startup construction meeting will be held with the engineer and the contractor present to answer any questions. The meeting date is Thursday October 10, 7pm-9pm at the Irricana Public Library.